The Wisconsin Depart-ment of Transportation (WisDOT) North Central Region provides interstate and state highway construction updates for Waushara County. Construction schedules may fluctuate pending weather conditions.

On WIS 21, 3rd Lane to Madison Street, Coloma, crews will continues working on installing curb and gutter, and placing concrete patches in the eastbound lane. Crews will be pacing base patches at the intersection of WIS 21 and Madison Street and will be placing concrete at the west end of the project. Motorists should expect flagging throughout the length of the project and the outside lane will be closed from the northbound I-39 off-ramp to Madison Street. The project is scheduled to finish June 20.

On I-39 Southbound, Cottonville Avenue to County O, crews will be continuing pavement removals and base pathing and grading. Motorists should expect single-lane closures with a reduced speed limit of 55 mpg and a maximum 12-foot width restriction. There is a 1.5-mile section with both lanes open between County C and Buttercup Avenue between north and south single lane closures. Both lanes of I-39 southbound will be open by noon on Friday, May 27 for Memorial Day weekend. The project is scheduled through Oct. 31.

On I-39 Southbound, Marquette County line to Cottonville Avenue, crews will pave, install guardrail, and place gravel should at the County CH and Czech Avenue structures. Crews will complete pavement removals and pave the driving lane and outside shoulder from County CH to 2.35 miles north, including the WIS 21 ramps. Crews will also be removing temporary barriers and installing pavement markings to allow both lanes to open by noon, Friday, May 27. Motorists should expect single-lane closures with a reduced speed limit of 55 mph and a 12-foot restriction. Both lanes of I-39 southbound will be open by noon Friday, May 27 for the holiday weekend. The project is scheduled through Aug. 5.

On WIS 22, Marquette county line/County JJ in the Town of Dakota to WIS 21 West/West Division Street in the City of Wautoma, crews will be working on pavement markings. Motorists can expect a paint marking convoy. The project should be finished on May 26.